Question 46 Selectable Answer
Which of the following can be part of the Sprint Backlog?

Answer:
Explanation:
Anything that is created during the decomposing Product Backlog items can be part of the Sprint Backlog.
Question 47 Selectable Answer
What is the time box for the Sprint Planning (one-month Sprint)?

Answer:
Explanation:
Sprint Planning is timeboxed to a maximum of eight hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.
Question 48 Selectable Answer
In the Daily Scrum, the Developers are allowed to adjust their plan for the Sprint.

Answer:
Explanation:
The Daily Scrum is not the only time Developers are allowed to adjust their plan. They often meet throughout the day for more detailed discussions about adapting or re-planning the rest of the Sprintâ™s work.
Question 49 Selectable Answer
The Product Owner is basically a Project Manager 2.0.

Answer:
Explanation:
The Project Manager Roles responsibilities is to manage costs, resources, execution, etc. - the Product Owner instead is responsible for maximizing the Product Value!
Question 50 Selectable Answer
A Scrum Team member should take over both accountabilities Scrum Master and Product Owner.

Answer:
Explanation:
The Scrum Master and the Product Owner accountability should not be the same person. But: there is nothing in the Scrum Guide mentioning this (best practice).
Question 51 Selectable Answer
The Product Owner is responsible to define the Definition of Ready.

Answer:
Explanation:
There is no Definition of Ready in Scrum.
Question 52 Selectable Answer
The Developers recognize during the Sprint, that they will not manage to finish the planned work .
What should they do?

Answer:
Explanation:
The Product Owner has to be informed and the topic has to be discussed.
Question 53 Selectable Answer
Self-management means, that the team can decide which Scrum events are needed.

Answer:
Explanation:
All Scrum events listed in the Scrum Guide are mandatory.
Question 54 Selectable Answer
Which statement is true about the Product Backlog?

Answer:
Explanation:
The Product Owner is responsible for Product Backlog management and the creation of Product Backlog items. The Product Owner can delegate work to the Scrum team.
Question 55 Selectable Answer
The Product Backlog is the single source of work undertaken by the Scrum Team.

Answer:
Explanation:
The Product Backlog is an emergent, ordered list of what is needed to improve the product. It is the single source of work undertaken by the Scrum Team.
Question 56 Selectable Answer
Which two statements about the Developers are correct?

Answer:
Explanation:
The Definition of Done is owned by the Developers. Only the Developers are allowed to adjust it. The Product Owner can ask the Developers to help him/her with managing the Product Backlog, but the Developers do not have to help. It is the responsibility of the Product Owner to decide when to release. The Development Team is self-organized.
Question 57 Selectable Answer
The Sprint Review is a formal opportunity to inspect and adapt Scrum artifacts.

Answer:
Explanation:
Each event in Scrum is a formal opportunity to inspect and adapt Scrum artifacts.
Question 58 Selectable Answer
The Sprint Retrospective should be held at the same time and place to reduce complexity.

Answer:
Explanation:
Optimally, all events are held at the same time and place to reduce complexity.
Question 59 Selectable Answer
The Sprint Planning is a formal opportunity to inspect and adapt Scrum artifacts.

Answer:
Explanation:
Each event in Scrum is a formal opportunity to inspect and adapt Scrum artifacts.
Question 60 Selectable Answer
When does the Scrum Master cancel a Sprint?

Answer:
Explanation:
The Sprint can be cancelled by the Product Owner when the Sprint Goal becomes obsolet. The Scrum Master is not allowed to do this.