The Sprint Retrospective meeting is a time boxed Scrum event.
Answer: Explanation:
The Sprint Retrospective is a three-hour meeting for one-month Sprints.
Question 17Selectable Answer
What does a burn-down chart measure in a project?
Answer:
Question 18Selectable Answer
Which Scrum Event is timeboxed to a maximum of four hours?
Answer: Explanation:
The Sprint Review is the second to last event of the Sprint and is timeboxed to a maximum of four hours for a one-month Sprint. For shorter Sprints, the event is usually shorter.
Question 19Selectable Answer
All items in the Product Backlog have usually the same size.
Answer: Explanation:
Items at the top of the Product Backlog are usually smaller. They are more refined and decomposed.
Question 20Selectable Answer
What is the main accountability (roles = outdated term) of a Project Manager in Scrum?
Answer: Explanation:
There are no Project Managers in Scrum.
Question 21Selectable Answer
A Sprint can be cancelled when the Sprint Goal becomes obsolete.
Answer: Explanation:
A Sprint could be cancelled if the Sprint Goal becomes obsolete. Only the Product Owner has the authority to cancel the Sprint.
Question 22Selectable Answer
What are the advantages of shorter Sprints?
Answer: Explanation:
Shorter Sprints can be employed to generate more learning cycles and limit risk of cost and effort to a smaller time frame. Each Sprint may be considered a short project.
Question 23Selectable Answer
Which Scrum accountability (role = outdated term) is owning the Product Backlog?
Answer: Explanation:
To "own" something means, that you are accountable for it.
Question 24Selectable Answer
The Sprint length can be 6 weeks.
Answer: Explanation:
Sprints are fixed length events of one month or less to create consistency. A new Sprint starts immediately after the conclusion of the previous Sprint.
Question 25Selectable Answer
Which statement is not correct about the Scrum Daily?
Answer: Explanation:
It is not the task of the Scrum Master to moderate the Daily Scrum. The Scrum Master does not need to attend the Daily Scrum - only the Developers.
Question 26Selectable Answer
What is Velocity?
Answer: Explanation:
The Velocity of a team is the average amount of work (e.g. in Story Points) done per Sprint.
Question 27Selectable Answer
The Sprint is a time boxed Scrum event.
Answer: Explanation:
The Sprint is a time box of one month or less.
Question 28Selectable Answer
The Scrum Master in a Scrum Team is responsible for instilling quality by adhering to a Definition of Done.
Answer: Explanation:
Developers in a Scrum Team are responsible for instilling quality by adhering to a Definition of Done.
Question 29Selectable Answer
It is allowed to change the scope during a Sprint.
Answer: Explanation:
Scope may be clarified and renegotiated with the Product Owner as more is learned.
Question 30Selectable Answer
More Velocity means more Value!
Answer: Explanation:
There is no direct relationship between Velocity (speed) and value.