Question No : 1
How often should the composition of the team change?

Answer:
Explanation:
Sometimes you will see questions like this in the exam. You may know that the composition of the team should not change during the Sprint, yet, the correct choice here may imply that. Well, it is up to you to interpret it in a way that it doesn't mean such a thing!

Question No : 2
What is the time box for a Sprint?

Answer:
Explanation:
The Sprint is a time box of one month or less.

Question No : 3
The Scrum Master can decide which Scrum Events are required in the Scrum project.

Answer:
Explanation:
Scrum defines which Events are required in all Scrum project, not the Scrum Master. It is always required to have the Sprint Planning, the Daily Scrums, the Sprint Review and the Sprint Retrospective in every project.

Question No : 4
Which statement describes best how the Product Backlog is impacted by changes in the product environment?

Answer:
Explanation:
The Product Backlog should reflect the changes of the environment. The Product Owner should try to adapt the Product Backlog in a way, that the changes are reflected to maximize the product value.

Question No : 5
Only the Developers are influencing the Definition of Done, no one else.

Answer:
Explanation:
The organization should define a Definition of Done (minimum). The Developers should take this and add the team specifics.

Question No : 6
A new Sprint starts immediately after the conclusion of the previous Sprint - there is nothing in between of two Sprints.

Answer:
Explanation:
A new Sprint starts immediately after the conclusion of the previous Sprint.

Question No : 7
The Sprint Backlog content is emerging during the Sprint.

Answer:
Explanation:
There are 3 things in a Sprint Backlog:

Question No : 8
Which statement about the Product Backlog is correct?

Answer:
Explanation:
The Product Owner is responsible for managing the Product Backlog. It should be ordered by value and items at the bottom of the Product Backlog may be larger (not yet refined).

Question No : 9
The Sprint Review is an opportunity for inspecting and adapting in Scrum?

Answer:

Question No : 10
Multiple Scrum Teams working on the same product must have the same Sprint start/end.

Answer:
Explanation:
There is no rule in the Scrum guide how to handle the Sprint starts/endings in scaled Scrum.