- Reviews
Why Choose PassQuestion Microsoft 74-343 Exam Questions
Passquestion team uses professional knowledge and experience to provide Microsoft Project 74-343 Questions and Answers for people ready to participate in Managing Projects with Microsoft Project 2013 exam. The accuracy rate of 74-343 exam questions provided by Passquestion are very high and they can 100% guarantee you pass the Microsoft 74-343 exam successfully in the first attempt. Everyone can get 74-343 pdf with free test engine to study. PassQuestion can promise you always have the latest version for your Microsoft 74-343 test preparation and get your Microsoft Project certification easily.
74-343 Frequently Asked Questions
Q1: Can I use 74-343 exam Q&As in my phone?
Yes, PassQuestion provides Microsoft Project 74-343 pdf Q&As which you can download to study on your computer or mobile device, we also provide 74-343 pdf free demo which from the full version to check its quality before purchasing.
Q2: What are the formats of your Microsoft 74-343 exam questions?
PassQuestion provides Microsoft 74-343 exam questions with pdf format and software format, pdf file will be sent in attachment and software file in a download link, you need to download the link in a week, it will be automatically invalid after a week.
Q3: How can I download my 74-343 test questions after purchasing?
We will send Microsoft Project 74-343 test questions to your email once we receive your order, pls make sure your email address valid or leave an alternate email.
Q4: How long can I get my Microsoft Project 74-343 questions and answers after purchasing?
We will send Microsoft Project 74-343 questions and answers to your email in 10 minutes in our working time and no less than 12 hours in our off time.
Working Time:
GMT+8: Monday- Saturday 8:00 AM-18:00 PM
GMT: Monday- Saturday 0:00 AM-10:00 AM
Q5: Can I pass my test with your Microsoft Project 74-343 practice questions only?
Sure! All of PassQuestion Microsoft Project 74-343 practice questions come from real test. If you can practice well and get a good score in our practice Q&As, we ensure you can pass your Managing Projects with Microsoft Project 2013 exam easily.
Q6: How can I know my 74-343 updated?
You can check the number of questions, if it is changed,that means we have updated this exam ,you can contact us anytime to ask for an free update. our sales email : [email protected]
Q7: What is your refund process if I fail Microsoft 74-343 test?
If you fail your 74-343 test in 60 days by studying our study material, just scan your score report and send to us in attchment,when we check, we will give you full refund.
Q8. What other payment menthod can I use except Paypal?
If your country don't support Paypal, we offer another Payment method Western Union,it is also safe and fast. Pls contact us for the details, we will send it to your email.
Question No : 1
A.Open the old OfficeMove.mpp file, click on Save As, and save the file using a new file name.Then enter the project name in the Project Summary Task.Set all tasks to zero percent complete.
B.Open the old OfficeMove.mpp file, change the project start date and project title, and clear the baseline.Save the file using the current project name.
C.Open the old OfficeMove.mpp file, save the file as an .mpt file type, removing the baseline and actual values.Save the .mpt file as an .mpp file type, assigning the current project name.
D.Open the old OfficeMove.mpp file, click on Save As, save the file using a new file name, clear the baseline, and set all tasks to zero percent complete.
Question No : 2
A.Add all summary tasks to your timeline.Project Professional 2013 will automatically recognize and add all milestones on each stage to your Timeline view.Copy the full-size timeline and paste to the PowerPoint slide.
B.Add all summary tasks to your timeline.Add all milestones to your timeline.Copy the full-size timeline and paste to your PowerPoint slide.
C.Create a new Timeline view from existing tasks in your project plan.Drag the timeline into a blank PowerPoint slide.
D.Create a new Timeline view that automatically shows milestones for each stage of your project.Copy the full-size timeline and paste to your PowerPoint slide.
Question No : 3
A.Right-click the resource and reassign it to the underallocated resource.
B.Drag the underallocated resource on the task to reassign it.
C.Right-click the task and reassign it to the underallocated resource.
D.Drag one of the tasks from the overallocated resource to the Unassigned Tasks section.
Question No : 4
Using resource leveling in Project Professional 2013, you need to resolve the overallocation for Resource1 for the month of November only.
What should you do?
A.Set the priority of Project A to 1000 and the priority of Project B to 500.Change the leveling order to Standard, and select Level All.
B.Set the priority of Project A to 1000 and the priority of Project B to 500.Set the Leveling Range for November.Change the leveling order to Priority, Standard.Select Level Resource, and choose Resource1 and Level Now.
C.Set the priority of Project A to 500 and the priority of Project B to 1000.Set the Leveling Range for November.Change the leveling order to Standard and select Level Resource.Then choose Resource1 and Level Now.
D.Set the priority of Project A to 500 and the priority of Project B to 1000.Change the leveling order to Priority, Standard, and select Level All.
Question No : 5
A.Create a report by using the Visual Reports feature.Select Microsoft Excel and choose relevant data to view in the report.
B.Download and install the Microsoft Project to Pivot Table Tool and generate a new Excel Pivot Table by selecting the current project.
C.Use the Excel Data From Other Sources feature to access your project file.
D.Create a Report view by using the new Built-In Dashboards and Reports feature and export to Excel.
Question No : 6
You are informed that one of the projects is cancelled before it starts.As a result, you need to delete the project.
What happens in the resource pool after you delete the project?
A.The resource pool will prompt that the project is deleted the next time it is opened, allowing you to remove the project.
B.The resource pool will still reflect the resource needs of the deleted project.You need to refresh the resource pool to fix the issue.
C.The resource pool will still reflect the resource needs of the deleted project.You need to manually break the link to the deleted project.
D.The resource pool is automatically updated when you delete the project.
Question No : 7
A.Set task priority to 1000.
B.Set task priority to 0.
C.Set task priority to 100.
D.Set task priority to 1.
Question No : 8
You need a graphical view that shows the current schedule to baseline.Which view should you use?
A.Tracking Gantt view
B.Leveling Gantt view
C.Detail Gantt view
D.Gantt Chart view
Question No : 9
Team members often do not work at the same time when completing their work on the tasks.You need to resolve the overallocations by using the Resource Leveling function.What should you do?
A.Click the Level resources with a proposed booking type option.
B.Click the Level only within available slack option.
C.Click the Leveling can adjust individual assignments on a task option.
D.Click Clear Leveling.
Question No : 10
You need to resolve the negative Total Slack values.What should you do?
A.Re-assign resources that have more availability at the time of the negative slack.
B.Remove lag time from task relationships.
C.Remove as many constraints as possible.
D.Remove lead time from the task relationships.
Question No : 11
A.Create a material resource for Supplies and Software License.
B.Assign the Supply cost resource to Task H, assign the Software License cost resource to Task A, and enter the actual costs using the Task Usage - Cost table for both Task H and A.
C.Assign the Supply material resource to Task H, assign the Software License material resource to Task A, and enter the actual costs using the Task Usage - Cost table for both Task H and A.
D.Create a cost resource for Supplies and Software License.
Question No : 12
Your project schedule is showing task overallocation indicators in the Gantt chart view.You navigate to the Team Planner view to investigate more details regarding the over allocations.
You discover that the BA1 resource is overallocated and you need to see all assignments with details for BA1 to understand their current workload before making any assignment changes.
What should you do?
A.Click View, check Details, select Task Form then click on the BA1 resource.
B.Right-click the BA1 resource and select Information.
C.Click the BA1 resource and scroll to the end of the project.
D.Click View, check Details, select Resource Form then click on the BA1 resource.
Question No : 13
You need to know which future tasks could be affected as a result of the resource leaving your project.What should you do?
A.Sort all tasks by start date and check start dates of tasks that are scheduled after the Develop Software Delivery task.
B.Use the Task path function to check driven successors for the Develop Software Delivery task.
C.View the critical path for tasks that are successors to the Develop Software Delivery task.
D.View the Network diagram and filter for the predecessor tasks to Develop Software Delivery task.
Question No : 14
A.Click on the Task tab and select the Change Working Time button.Assign the weekend working calendar to the task.
B.Assign the task calendar to the task using the Task Information dialog box.
C.Right-click on the weekend on the Gantt chart and select the weekend working calendar.
D.Change the start date of the task to the Saturday, which will assign the weekend working calendar to the task.
Question No : 15
A.For each new project, use the Status Bar to set new tasks to be auto scheduled.
B.Set the Default task type to Auto Scheduled for All New Projects in the Schedule Options.
C.For each new project, use the Auto Schedule button on the Tasks tab.
D.Set the New tasks created option to Auto Scheduled and set the Schedule Options to All New Projects.
E.Open the Global.mpt and use the Auto Schedule button on the Tasks tab.